| |
Home >
Portfolio > Office/Retail
Construction >
Baseline Consultants Office Building
Baseline Consultants
Office Building – Vestavia Hills, AL
The Baseline Consultants’
Office Building project is a significant project for Twin
Commercial, LLC for many
reasons, as good as any being the fact that it was the emerging
contractor’s first building completed in the greater Birmingham
area, and only its second project completed in the history of the
new company. The pride in this project stems from every aspect of
its success, from the initial discussions with the owner regarding
how Twin Commercial could add unique value to the project, to the
methodical detail in completing the punchlist, allowing the owner to
occupy the building well in advance of the scheduled completion
time.
The owner, Baseline
Investments, LLC needed a company that could complete the project
quickly and under budget. Relying on Twin Commercial’s interest to
prove itself as a new general contractor, its ability to scope and
prepare the trade packages during preconstruction to ensure the best
pricing, and its “open book” policy of reviewing the budget with the
owner as a team, Baseline took a calculated risk and selected Twin
Commercial from the list of general contractors they were
considering. A unique emphasis was placed on the preconstruction
phase to ensure all aspects of the project were planned so the
trades could be bought out early, allowing more time during the
project for quality control and detailed management. Several rounds
of value analysis and cost savings proposals were completed, and the
project broke ground on January 2, 2007 with a scheduled contract
time of eight (8) months.
Almost immediately, challenges
were encountered. Geotechnical reports confirmed that the building
pad was on fill material, and the structural engineer would require
deep foundations on one side of the building to ensure adequate
bearing capacity of the soil, and additional proof-rolling to
confirm compaction of under-slab fill. To further complicate
matters, the under-slab waste piping was installed incorrectly by
the plumbing subcontractor. Twin Commercial’s quality control review
caught the incorrect plumbing the morning of the slab pour, and the
plumbers worked with the concrete crew to correct the plumbing
during the pour, averting a potential disaster. With some
cooperation from the weather, and some innovative scheduling, the
deep foundation and slab was completed within the bounds of the
original schedule.
Some additional challenges
were encountered during installation of the site utilities. Site
domestic water service was not located on the property as shown on
the site utility plan. This problem was identified early in the
project by the superintendent’s attention to detail, and with some
coordination with the authorities having jurisdiction, the domestic
water was allowed to be extended from the main in the same trench as
the planned fire water service extension to the property – a
resourceful and economical solution for the owner. Prior to backfill
of the fire vault, Twin Commercial noticed that the vault had been
installed by the subcontractor out of level, and was also not
oriented properly to receive site ductile iron piping. Again,
quality control reviews caught the problem before it was magnified,
saving the subcontractor from a costly and time consuming mistake,
and saving significant time on the overall schedule. With the
project being the first out of the ground in a commercial
subdivision of nine (6) lots, Twin Commercial was required to take
the lead on several items of coordination outside the contracted
scope of responsibility, including distribution of power and water
to the property.
On the interior, quality of
the finishes was of the utmost importance. Twin Commercial reviewed
the work of each trade during installation as if through the eyes of
the owner and architect. The majority of deficient work items were
addressed during the project instead of at the end, allowing for a
very manageable punchlist after substantial completion. When the
work of the concrete staining subcontractor was not acceptable after
review of the initial installation, Twin Commercial, considering all
options and deadlines, decided to strip the seal from the floor and
self-perform the re-staining and re-sealing of the concrete to the
satisfaction of the owner.
Twin Commercial worked very
closely with the building inspectors, design team, and other
authorities having jurisdiction over the project. When the building
inspector, during the framing inspection, required that the
structural engineer write a letter certifying the installation of
the floor and roof trusses, the structural engineer’s schedule was
coordinated so that he could be on the job the next day for an
inspection. The resulting letter added special connections at
certain trusses depending on their uplift load criteria.
Immediately, Twin Commercial analyzed and color coded the truss shop
drawings for the framing subcontractor in order to simplify their
interpretation of the new connection locations. The total process
took only three (3) days, minimizing the impact to the schedule.
Safety was a primary concern
on this project. The superintendent, just prior to breaking ground,
completed the forty (30) hour OSHA safety course presented by the
ABC Alabama Chapter. Attendance to weekly toolbox meetings was
documented and was required of all subcontractors. Several special
safety meetings were held onsite, including scaffold safety for the
masons and framers, and fall protection for the roofers.
The project was able to stay
on schedule for many reasons, as important as any being that the
general contractor and owner agreed to meet weekly throughout the
project to review progress, make crucial decisions, and answer
questions. The communication on the project was of paramount
importance, flowing down from the owner and general contractor to
the subcontractors and suppliers. The superintendent and project
manager shared the same values relative to preparation,
organization, and communications, making the project progress
forward like a well-oiled machine. Twin Commercial field personnel
rose to the challenge and accepted more responsibility as the
project progressed. Job cost and labor was tracked and projected on
a bi-weekly basis, ensuring that the project stayed under budget.
Upcoming activities were reported to the owner in the weekly
Owner/GC meetings in anticipation of, and in preparation for,
potential changes that would be made. The result was a project that
was completed in six (6) months; two (2) months earlier than
originally anticipated, without compromising the expected quality.
The success described above
was the result of several project management plans and programs
implemented during the course of construction. Requests for
information were forwarded to the owner and architect in writing,
and tracked for response time. Owner/GC meeting agendas were
published in advance of the meeting, allowing all parties to prepare
and have answers at the meeting. After the meetings, the minutes
were documented and distributed to all parties. Changes in the work
were tracked as Contract Change Requests (CCRs), logged, and
priced
to the owner as soon as the change was realized by the general
contractor. CCR logs were reviewed at every Owner/GC meeting. Change
orders were submitted in a timely manner so that the budget stayed
current. Deficient work of subcontractors was documented, logged,
and forwarded to the subcontractors in writing. Outstanding
deficient work was reviewed with each subcontractor prior to
approval of payment applications. These proven but not always used
methods facilitated efficiency, communication, and accountability
and helped the project to flow smoothly.
Countless factors played roles
in the success of the Baseline Consultants’ Office Building, but
above all, the teamwork approach was bought into by everyone
involved in the project, setting up the project and the team for
success. For this reason, the project was considered a very special
one, and deserves recognition and qualification for an ABC
Excellence in Construction Award.
|